Appendix D - Saturn R&D Funding History

Army NASA
Fiscal Year 50 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 NASA
Run-Out
Total
Funding (Code)
Saturn I (931) 20.6 64.3 97.4 191.4 254.5 177.7 32.0 0.2 838.1*
Saturn IB (932) 18.3 140.0 258.7 248.7 194.0 101.1 42.1 1,002.2
Saturn V (933) 56.0 338.7 753.2 957.0 1,105.2 1,020.6 853.9 528.4 477.8 234.2 196.1 18.4 6,539.5
Engine Devel. (940) 10.0 23.8 77.7 103.9 135.1 166.0 166.3 133.2 49.8 20.5 7.1 6.7 900.1
Launch Ops (950) & Sys Engr. (980) 2.1 2.0 4.1
Spacraft (Lunar Rover) (914) 0.2 0.3 19.3 18.9 0.7 39.4
Total 30.6 88.1 175.1 353.4 748.6 1,236.9 1,413.3 1,487.3 1,264.4 975.7 577.9 503.8 253.1 196.8 18.4 9,323.4
Costs
Saturn I 7.4 32.4 59.8 101.8 246.5 320.3 65.3 5.1 0.3 -0.3 -0.1 -0.2 -0.1 -0.1 838.1
Saturn IB 2.7 74.1 243.2 304.8 217.7 108.7 48.2 1.7 0.9 0.3 0.5 -0.1 -0.5 1,002.2
Saturn V 22.0 229.5 638.0 999.6 1,174.8 1,048.9 792.5 653.2 436.0 260.0 198.5 93.5 -5.9 -0.1 -0.1 6,539.5
Engine Devel. 3.6 22.2 60.2 108.4 133.5 160.1 160.6 147.4 58.1 23.3 13.3 9.2 0.1 0.1 900.1
Launch Ops/Sys Engr. 0.5 2.8 0.8 16.8 21.2 1.2 4.1
Spacecraft (Lunar Rover) 39.4
Total 11.0 54.6 120.0 232.2 612.7 1,195.3 1,469.5 1,632.1 1,325.0 924.2 714.6 463.5 282.1 200.0 94.0 -6.0 -0.6 -0.8 9,323.4

* Includes Army (pre-NASA) funding of $84.9 million.

Note: Later-year credits result from final contract audits. Audit agency workload delays contract close-out several years in some cases.