APPENDIX 3 - VEHICLE MANUFACTURING AND TESTING HISTORIES
Table A - Gemini Launch Vehicle
Item | Gemini Titan Launch Vehicle | |||||
---|---|---|---|---|---|---|
GLV-1 | GLV-2 | GLV-3 | GLV-4 | GLV-5 | GLV-6 | |
Major welding of propellant tanks at Denver began. | Sept. 1962 | Sept. 1962 | June 1963 | Nov. 1963 | Jan. 1964 | Apr. 1964 |
Propellant tanks delivered to Baltimore | Oet. 10, 1962 | July 12, 1963 | Dec. 13, 1963 | Mar. 6, 1964 | June 25, 1964 | Aug. 16, 1964 |
Assembly completed | May 21, 1963 | Jan. 9, 1961 | June 6, 1964 | Sept. 4, 1964 | Dec. 9, 1964 | Feb. 25, 1965 |
Horizontal tests completed | May 27, 1963 | Jan. 17, 1964k | June 17, 1961 | Oct. 23, 1961 | Jan. 7, 1965 | Apr. 3, 1965 |
Erected in vertical test facility | June 9. 1963 | Feb. 7, 1964 | June 22, 1964 | Oct. 28, 1964 | Feb. 8, 1965 | Apr. 15, 1965 |
Power appled | - | Feb. 20, 1964 | - | Nov. 4, 1961 | Feb. 15, 1965 | May 13, 1965 |
Subsystems Function Verification Tests completed | - | - | July 31, 1961k | Nov. 19, 1964 | Mar. 8, 1965 | June 22, 1965 |
Combined Systems Acceptance Test completed. | Oct. 4, 1963a | Apr. 22, 1964 | Sept. 30, 1964b | Nov. 25, 1964 | Apr. 21, 1965 | June 25, 1965 |
Vehicle Acceptance Team Inspection | Oct. 8, 1963a | Apr. 27, 1964 | Oct. 7, 1964b | Dec. 11, 1964m | Apr. 26, 1965 | July 7, 1965 |
DD-250 | Oct. 12, 1963 | June 22, 1964 | Nov. 18, 1964 | Mar. 21, 1965 | May 15, 1965 | July 31, 1965 |
Delivered to ETR | Oct. 26, 1963 | July 11, 1964 | Jan. 23, 1965c | Mar. 23, 1965 | May 18, 1965 | Aug. 2, 1965 |
Erection at complex 19 completed | Oct. 29, 1963 | Sept. 14, 1964* | Jan. 25, 1965 | Mar. 29, 1965 | June 7 1965 | Aug. 31, 1965 Dec. 5, 1965 |
Power applied | Nov. 13, 1963 | - | Jan. 20, 1965 | - | - | - |
Subsystem and Combined Systems tests completed | Jan. 21, 1964j | Oct. 20, 1964 | Feb. 15, 1965 | Apr. 16, 1965 | June 29, 1965 | Sept. 16, 1965 |
Tanking exercise | - | - | - | - | - | - |
Spacecraft mated to GLV | Mar. 5, 1964 | Nov. 5, 1964 | Feb. 17, 1965 | Apr. 23, 1965 | July 7, 1965 | Sept. 17, 1965. Dec. 5, 1965 |
Joint Combined Systems Tests | - | Nov. 18, 1961 | Feb. 24, 1965 | Apr. 30, 1965 | - | - |
Countdown practice exercises completed - Wet Mock Simulated Launch. | Apr. 2, 1964 | Nov. 24, 1964 | Mar. 8, 1965 | May 13, 1965 | July 22, 1965 | Oct. 7, 1965 |
Final Status Simulated Flight Test | Apr. 5, 1961 | Jan. 14, 1965d | Mar. 17, 1965 | May 20, 1965 | Aug. 12, 1965 | Oct. 19, 1965. Dec. 5, 1965 |
Launch | Apr. 8, 1964 | Jan. 19, 1965d | Mar. 23, 1965 | June 3, 1965 | Aug. 21, 1965 | Oct. 25, 1695.8 Dec. 15, 1965.* |
Item | Gemini Titan Launch Vehicle | |||||
---|---|---|---|---|---|---|
GLV-7 | GLV-8 | GLV-9 | GLV-10 | GLV-11 | GLV-12 | |
Major welding of propellant tanks at Denver began. | May 1964 | Sept. 1964 | Feb. 1965 | Apr. 1965 | June 28, 1965 | Nov. 22, 1966 |
Propellant tanks delivered to Baltimore | Feb. 25, 1965 | Apr. 15, 1965 | Aug. 16, 1965 | Sept. 21, 1965 | Nov. 3, 1965 | Jan. 20, 1966 |
Assembly completed | May 20, 1965 | - | Nov. 10, 1965 | Feb. 28, 1966 | Apr. 5, 1966 | June 1, 1966 |
Horizontal tests completed | June 14, 1965 | Sept. 16, 1965 | Nov. 23, 1965 | Mar. 3, 1966 | Apr. 25, 1966 | June 14, 1966 |
Erected in vertical test facility | June 28, 1965 | Sept. 28, 1965 | Dec. 10, 1965 | Mar. 7, 1966 | Apr. 29, 1966 | June 22, 1966 |
Power appled | July 26, 1965 | Oct. 13, 1965 | Dec. 22, 1965 | Mar. 14, 1966 | May 9, 1966 | July 6, 1966 |
Subsystems Function Verification Tests completed | Aug. 25, 1965 | Nov. 4, 1965 | Jan. 20, 1966 | Apr. 13, 1966 | June 8, 1966 | July 11, 1966 |
Combined Systems Acceptance Test completed. | Sept. 20, 1965 | Nov. 8, 1965 | Feb. 9, 1966 | Apr. 14, 1966 | June 9, 1966 | July 29. 1966 |
Vehicle Acceptance Team Inspection | Sept. 28, 1965 | Nov. 16, 1965 | Feb. 15, 1966 | Apr. 26. 1966 | June 20. 1966 | Aug. 9, 1966 |
DD-250 | Oct. 15, 1965 | Dec. 23, 1965 | Mar. 8, 1966 | May 18, 1966 | - | - |
Delivered to ETR | Oct. 19, 1965 | Jan. 6, 1966 | Mar. 10, 1966 | May 20, 1966 | July 12, 1966 | Sept. 3, 1966 |
Erection at complex 19 completed | Oct. 29, 1965 | Jan. 13, 1966 | Mar. 24, 1966 | June 8, 1966 | July 22, 1966 | Sept. 16, 1966 |
Power applied | Oct. 31, 1965 | Jan. 19, 1966 | Mar. 30, 1966 | June 9, 1966 | July 27, 1966 | Sept. 19, 1966 |
Subsystem and Combined Systems tests completed | Nov. 12, 1965 | Feb. 1, 1966 | Apr. 12, 1966 | June 17, 1966 | Aug. 5, 1966 | Oct. 10, 1966 |
Tanking exercise | - | Feb. 18, 1966 | Apr. 20, 1966 | June 24, 1966 | Aug. 15, 1966 | Oct. 12, 1966 |
Spacecraft mated to GLV | Nov. 22, 1965 | Mar. 5, 1966 | May 8, 1966 | July 5, 1966 | Aug. 24 1966 | Oct. 25, 1966 |
Countdown practice exercises completed - Wet Mock Simulated Launch. | - | Mar. 9, 1966 | May 10, 1966 | July 13, 1966 | Aug. 31, 1966 | Nov. 1, 1966 |
Final Status Simulated Flight Test | Nov. 27, 1965 | Mar. 10, 1966 | May 11, 1966* | July 13, 1966 | Sept. 1, 1966 | Nov. 2, 1966 |
Launch | Dec. 4, 1965 | Mar. 16, 1966 | June 3, 1966g | July 18, 1966 | Sept. 12, 1966h | Nov. 11, 1966i |
- GLV-1 not accepted after first CSAT (Sept. 6, 1963) and VAT inspection (Sept. 11, 1963).
- GLV-3 not accepted after first CsAT (Aug. 7, 1961) and VAT inspection (Aug. 17, 1964).
- First erected July 14, 191, and Subsystem tests began July 17, nullified by lightning strike Aug. 17. Hurricane Cleo caused stage II deerection Aug. 28; reerected Aug. 31. Hurrlane Dora caused vehicle deerection Sept. 8.
- Alter SFT on Dec 3, 1961, launch scheduled for Dec. 9 aborted at ignition plus 1.7 sec.
- Scrubbed because of Agena catastrophic failure.
- Aborted Dec. 12, 1965, at ignition plus 1.16 sec when umbilical tailplug dropped prematurely. Investigation also revealed dust cover in gas generator.
- Mission postponed May 17 when GATV failed to orbit. SFT repeated May 26. Mission again scrubbed on June 1 because of spacecraft computer problem.
- Mission scrubbed Sept. 1 because pinhole discovered in oxidizer tank. Rescheduled for Sept. 10; scrubbed because of AGE oversensitivity.
- Mission postponed on Nov. 8 because of malfunction in secondary autopilot; postponed again on Nov. 1 for malfunction in new autopilot.
- Sequence compatibility fring (SCF).
- POGO kit installed Jan. 20-Feb. 5.
- Modified at Baltimore alter GT-2 tandem actuator trouble at the Cape - actuator replaced Jan. 8.
- Delay from Dec. 19 - Mar. 10, 1966, permitted modifications at Baltimore that were usually done at the Cape.
Table B - Gemini Target Vehicle
Item | Stage Completed | |||||||
---|---|---|---|---|---|---|---|---|
5001 | 5002 | 5003 | 5004 | 5005 | 5006 | 5001R | ||
Basic vehicle | Apr. 30, 1964 | Dec. 17, 1964 | July 20, 1965 | Oct. 25,1965 | Feb. 2, 1966 | Mar. 22, 1966 | Nov. 23, 1965* | |
Modifcation and final assemby | Sept. 24, 1964 | May 18, 1965 | Oct. 14, 1965 | Jan. 26, 1966 | Apr. 12, 1966 | June 6, 1966 | July 21, 1966** | |
Combined Systems Acceptance Test | May 6, 1965 | June 30, 1965 | Jan. 8, 1966 | Feb. 27, 1966 | May 3, 1966 | June 27, 1966 | Aug. 15, 1966 | |
Vehicle Acceptance Team Inspection | May 27. 1965 | July 23, 1965 | Jan. 18, 1966 | Mar. 11, 1966 | May 14, 1966 | July 13, 1966 | Sept. 2, 1966 | |
Delvered to ETR | May 29, 1965 | July 25, 1965 | Jan. 21, 1966 | Mar. 14, 1966 | May 16, 1966 | July 15, 1966 | Sept. 4, 1966 | |
Preliminary systems tests at Hangar E | July 8, 1965 | Aug. 23, 1965 | Jan 26, 1966 | Mar. 21, 1966 | June 1, 1966 | July 21, 1966 | Sept. 16, 1966 | |
Interface tests, Plan X | – | Sept. 1, 1965 | Jan. 28, 1986 | Mar. 23, 1966 | June 8, 1966 | July 26, 1966 | Sept. 20, 1966 | |
Systems tests at Hangar E | - | Sept. 30, 1965 | Feb. 28, 1966 | May 1, 1966 | July 1, 1966 | Aug. 20, 1966 | Oct. 22, 1966 | |
Target and launch vehicles mated. | July 8, 1965 | Oct 1, 1965 | Mar. 1, 1966 | May 2, 1966 | July 2, 1966 | Aug. 22, 1966 | Oct. 23, 1966 | |
Systems tests at complex 14 | July 26, 1965 | Oct. 20, 1965 | Mar. 9, 1966 | May 10, 1966 | July 12, 1966 | Aug. 31, 1966 | Nov. 1, 1966 | |
Launch | - | Oct. 25, 1965 | Mar. 16, 1966 | May 17, 1966 | July 18, 1966 | Sept. 12, 1966 | Nov. 11. 1966 |
* 5001 was returned trom ETR for refurbishing on this date and designated 5001 R.
** 5001 R was completely disassembled and rebuilt.
Note: GATV was a modifled standard Agena. a production-line vehicle delivered to the Gemini program as GFE through the standard DD-250 procedure; when delivered it was considered to be flight ready, After modification and reassembly, the same tests certified its readiness ss the Gemini Agena Target Vehicle.
Table C - Gemini Target Launch Vehicle
Item | Gemini Target Launch Vehicle | ||||||
---|---|---|---|---|---|---|---|
TLV-5301 | TLV-5302 | TLV-5303 | TLV-5304 | TLV-5305 | TLV-5306 | TLV-5307 | |
Basic vehicle delivered | — | Apr. 2, 1965 | - | Dec. 2, 1965 | Nov. 1, 1965 | Jan. 14, 1966 | Apr. 11, 1966 |
Final assembly of booster and sustamer sections | - | May 25, 1965 | - | Jan. 19, 1966 | Feb. 15, 1966 | Mar. 17, 1966 | July 27, 1966 |
Install flight equipment and Gemini-pecular kit. | - | June 3, 1965 | - | Jan. 24, 1966 | Feb. 18, 1966 | June 20, 1966 | Aug. 22, 1966a |
Systems test completed | - | July 13, 1965 | - | Mar. 14, 1966 | June 1, 1966b | July 1, 1966 | Sept. 9, 1966 |
Composite test | - | July 22, 1965 | - | Mar. 23, 1966 | June 3, 1966 | July 11, 1966 | Sept. 12, 1966 |
Data review and final acceptance | - | July 29. 1965 | - | Mar. 31, 1966 | June 6. 1966 | July 15, 1966 | Sept. 15, 1966 |
Delivered to ETR | Dec. 4, 1964 | Aug. 11, 1965 | Feb 13, 1966 | May 8, 1966 | June 9, 1966 | July 18, 1966 | Sept. 19, 1966 |
Erected | - | Jan 5, 1960 | - | May 21, 1966c | June 15, 1966 | July 28, 1966 | Sept. 26, 1966 |
Subsvstems tests completed | - | Feb. 23. 1966 | - | May 2S, 1966 | June 28. 1966 | Aug. 10, 1966 | Oct. 18, 1966 |
TLV/GATV mate | Oct. 10, 1965 | Mar. 1, 1966 | May 2, 1966 | May 25, 1966 | July 1, 1966 | Aug. 22, 1966 | Oct. 23, 1966 |
Joint Flight Acceptance Composite Test | - | Mar. 7, 1966 | - | May 30. 1966 | July 7, 1966 | Aur. 26.1966d | Oct. 28, 1966 |
Simultaneous launch | Oct. 20, 1965 | Mar. 9, 1966 | May 10, 1966 | - | July 12, 1966 | Aug. 31, 1966 | Nov. 1, 1966 |
Launch | Oct. 25, 1965 | Mar. 6, 1966 | May 17, 1966 | June 1, 1966 | July 18, 1966 | Sept. 12, 1966e | Nov. 11. 1966 |
- This vehicle had originally been asigned to the Lunar Orbiter program: the loss of the TLV on Gemini IX made necessary an additional Atlas for the Gemini program.
- System tests were completed Mar. 25, 1966, but components were then reworked to latest flight configuration, Mar. 26-May 26, 1966; system tests were then rerun.
- Vehicle in storage May 11-17, 1966, and undergoing modification for ATDA mission from May 18-20.
- This test was repeated Sept. 1. 1966.
- Launches were attempted Sept. 9 and 10, 1966.
Table D - Gemini Spacecraft
Item | S/C 1 | S/C 2 | S/C 3 | S/C 4 | S/C 5 | S/C 6 |
---|---|---|---|---|---|---|
Equipment installation | - | June 30, 1964 | Sept. 12, 1964 | Jan. 31, 1965 | Mar. 14, 1965 | May 4, 1965 |
Reentry/adapter mate | - | July 7, 1964 | Sept. 27, 1964 | Feb. 23, 1965 | Apr. 1, 1965 | May 12, 1965 |
Systems Assurance Tests | - | - | - | Mar. 2, 1965 | Apr. 20, 1965 | June 15, 1965 |
Environmenta control system validation | - | - | - | - | - | - |
Simulated Flight Test | - | Sept. 16, 1964 | Dec. 21, 1964 | Mar. 8, 1965 | May 19, 1965 | June 25, 1965 |
Altitude chamber test | Sept. 23, 1963 | - | Nov. 18, 1964 | Mar. 25, 1965 | June 1, 1965 | July 21, 1965 |
Shipped to ETR | Oct. 4, 1963 | Sept. 21, 1964 | Jan. 4, 1965 | Apr. 4, 1965 | June 19, 1965 | Aug. 4, 1965 |
Complex 19/EIIV and G&C | Mar. 3, 1964 | Oct. 18, 1964 | Feb. 4, 1965 | Apr. 14, 1965 | June 26, 1965 | Sept. 9, 1965 |
Mechanical mate | Mar. 5, 1964 | Nov. 5, 1964 | Feb. 17, 1965 | Apr. 23, 1965 | July 8, 1965 | Sept. 18, 1965 |
Joint Combined Systems Test | - | Nov. 19, 1964 | Feb. 24, 1965 | Apr. 30, 1965 | July 13, 1965 | Sept. 24, 1965 |
FCMT/Final Systems Test | - | - | Mar. 3, 1965 | May 7, 1965 | July 16, 1965 | Oct. 10, 1965 |
Wet Mock Simulated Launch/ Simultaneous Launch Demonstration. | Apr. 3, 1964 | Nov. 24, 1964 | Mar. 8, 1965 | May 13, 1965 | July 22, 1965 | Oct. 7, 1965 |
Final Simulated Flight Test | Apr. 6, 1964 | Jan. 14, 1965 | Mar. 18, 1965 | May 29, 1965 | Aug. 13, 1965 | Dec. 9, 1965 |
Launch. | Apr. 8, 1964 | Jan. 19, 1965 | Mar. 23, 1965 | June 3, 1965 | Aug. 21, 1965 | Dec. 15, 1965 |
Item | S/C 7 | S/C 8 | S/C 9 | S/C 10 | S/C 11 | S/C 12 |
---|---|---|---|---|---|---|
Equipment installation. | June 29, 1965 | Sept. 17, 1965 | Dec. 7, 1965 | Jan. 29, 1966 | Apr. 13, 1966_ | June 4, 1966 |
Reentry/adapter mate. | July 26, 1965 | Sept. 20, 1965 | Nov. 22, 1965 | Feb. 4, 1966 | Apr. 8, 1966 | June 13, 1966 |
Systems Assurance Tests | Aug. 12, 1965 | Oct. 22, 1965 | Dec. 30, 1965 | Mar. 2, 1966 | Apr. 29, 1966 | June 30, 1966 |
Environments control system validation. | - | Oct. 22, 1965 | Jan. 11, 1966 | Mar. 21, 1966 | May 9, 1966 | July 7, 1966 |
Simulated Flight Test | Aug. 30, 1965 | Nov. 4, 1965 | Jan. 21, 1966 | Apr. 5, 1966 | May 20, 1966 | July 30, 1966 |
Altitude chamber test | Sept. 17, 1965 | Dec. 13, 1965 | Feb. 10, 1966 | Apr. 28, 1966 | June 15, 1966 | Aug. 20, 1966 |
Shipped to ETR. | Oct. 9, 1965 | Jan. 8, 1966 | Mar. 2, 1966 | May 13, 1966 | July 7, 1966 | Sept. 6, 1966 |
Complex 19/EIIV and G&C | Oct. 30, 1965 | Feb. 11, 1966 | Apr. 14, 1966 | June 21, 1966 | Aug. 9, 1966 | Oet. 6, 1966 |
Mechanical mate | Nov. 22, 1965 | Mar. 6, 1966* | May 8, 1966** | July 5, 1966 | Aug. 24, 1966 | Oct. 25, 1966 |
Joint Combined Systems Test. | Nov. 15, 1965 | Feb. 16, 1966 | Apr. 19, 1966 | June 23, 1966 | Aug. 12, 1966 | Oct. 10, 1966 |
FCMT/Final Systems Test. | - | Feb. 23, 1966 | Apr. 28, 1966 | July 1, 1966 | Aug. 23, 1966 | Oct. 19, 1966 |
Wet Mock Simulated Launch/ Simultaneous Launch Demonstration. | - | Mar. 9, 1966 | May 10, 1966 | July 12, 1966 | Sept. 1, 1966 | Nov. 1, 1966 |
Final Simulated Flight Test. | Nov. 27, 1965 | Mar. 10, 1966 | May 11, 1966 | July 13, 1966 | Sept. 2, 1966 | Nov. 2, 1966 |
Launch | Dec. 4, 1965 | Mar. 16, 1966 | June 3, 1966*** | July 18, 1966 | Sept. 12, 1966† | Nov. 11, 1966 |
* Temporary mate and erector cycling Feb. 25, 1966
** Soft mate and erector cycling May 3, 1966.
*** Mission scrubbed May 17, 1966, when GATV failed to orbit: systems retest, mate, and EIIV retest completed May 21, repeat of FST May 26. Mission again scrubbed June 1. 1966, because of spacecraft computer problem, followed by recycle and launch
† Launch attempts on Sept. 9 and 10, 1966.